Quantcast

MTC/SDMBA Trail Maintenance: May 15th, Los Pen

TRAIL MAINTENANCE EVENT: MAY 15TH, 8AM- NOON
LOS PENASQUITOS CANYON PRESERVE


Please set your calendar and come out to meet fellow riders, improve some local trails and have a good time at the Trail Maintenance Event in Los Penasquitos Canyon Preserve on May 15th.

In January, our trail maintenance event generated almost 40 volunteers and major renovations to nine sections of Cobblestone Trail. Since that time, the Rangers have decided to feature Cobblestone as an example of a good example of multiuse trails that aren’t just a dirt road, and there are more rut-repairs, drainage installation and brush trimming to complete before National Trails Day, on June 5th.

This trail event is jointly sponsored by cyclist, running and equestrian organizations, and we’ll be working together on trails we all share.

We'll meet at the upper trailhead to Cobblestone Trail (directions
below) and then hike our tools and equipment down to the worksites. We'll be performing more repairs and grading to the sections of Upper Cobbles not finished in January, clearing light brush along Cobblestone and adjacent trails and repairing ruts and erosion on the bicycle route in Lower Cobbles. The Ranger has identified our work areas and will allocate volunteer labor for appropriate repair work.

DIRECTIONS: The meeting point will be at the top of Cobblestone
Trail, on the Del Mar Mesa. To get there, take the 56 Freeway to
Carmel Country Rd, south. Then take Carmel Country Rd to Del Mar Mesa Rd (Shaw Ridge Rd) east/left. Follow Shaw Ridge Rd to the point where it "tees" into Del Vino. Turn right onto Del Vino and park at the end of Del Vino. The top of Cobblestone is to the southeast of the end of the pavement. Walk south onto the dirt road, then turn left at the first track you see: it leads directly to the trailhead and you'll see the Ranger's truck there. The meeting time to start work is 8:00am, but if you come later, you will be appreciated (see below).

Notes on Trail Maintenance: if you haven't come to one of these
events before, you will enjoy it, even if you do break a sweat. There will be tools for working available, but you can bring your own (mark it with your name using a Sharpie) if you like. Certainly, bring a hat, some water and work gloves. These "work parties" usually go about 4 or 5 hours, so if you're late, it will still work out fine.

Come by! Lend a hand, whether it is in "hard labor", walking water up and down the trail to workers or just cheering others on and taking photos. We guarantee you'll enjoy meeting and working with the people you share trails with!

If you are planning to come, please email an RVSP to:
MultiUseTrails-owner@yahoogroups.com, so we can give an expected count to the Rangers. If you have questions, email them to the same place and we'll try to get back to you quickly.

Here's hoping to see you out there!
Last Time: the truly hardcore went out for a ride afterwards... want to get hammered by Marissa Brand after working 4 hours in the sun? Bring your bike...

heh heh...writin' checks on her account... :devil:
 
About 18 riders showed up. All were bike-riders, as opposed to any from the two equestrian organizations that we advertised the event to. (Just to make you feel good that, even if you didn't come, it was the hairy-legged mountainbikers that showed up.)

Only a few for here:


The sluiced area of Upper Cobbles.


Same area, now filled in at the center and being sloped to drain off the side.


Same area, but shot while standing a little to the right. Trail now looks wider, but debris used to suggest a narrow track, anyway.


"red ruts", a section that funnels water entering the trail from the left side of the photo, plus from the old "sluice" and shoots it down the trail.


Looking down red ruts as we break out the side for sheet drainage.


Red ruts, afterward. Very hard to see, but a berm/cross-drain at the top where the water comes off the slope, then opened up for sheet drainage, then a 3/4 width berm and drain, and finally, a transition and hardline for riding, on the left.

All that disturbed soil is pretty loose right now, though. A quick set of afternoon showers would really fit the bill. Maybe in early June...